A work center has five jobs assigned to it. They are labeled inthe order of their arrival in the shop as jobs A B C D and E.The work center may work on only one job at a time and mustcomplete any job it starts before starting another job. Job A has aprocessing time of 6 days and is due to the customer in 9 days. JobB has a processing time of 2 days and is due in 16 days. Job C hasa processing time of 4 days and is due in 10 days. Job D has aprocessing time of 3 days and is due in 7 days. Job E has aprocessing time of 5 days and is due in 12 days. Using the earliestdue date (EDD) priority rule what will be the average lateness ofthese orders?