Assume you have bought an old
semi-furnished house and need to renovate it before moving in. Generally
renovation work can be of different categories such as furniture electrical
equipment plumbing landscaping (garden) and painting. You will have to
engage an external agency to get a portion of this work completed. However
before you start the whole renovation effort you need to decide on two
aspects: the amount of time required for the whole project and the cost to
complete the renovation.Determine the need to develop the WBS
before defining the activities in every instance. In the given scenario think
of the different types of dependencies within the project. In your opinion how
do the activity dependencies impact the project duration? Explain why control
accounts are identified in the WBS.Determine whether a WBS is necessary for
every project irrespective of its scope. Do you think a WBS is needed for a
project where the scope is only to renovate the living room which includes
furniture and painting as major deliverables