Here are some thoughts for your consideration:1. Confirm the duration of Tasks 21 and 22 by typing a value in the Duration field eliminating the ?2. Review the parallel tasks that can lead to overallocated resources (i.e. Tasks 7 and 8)3. Check the timing of the development and delivery of training. What if changes are required as a result of the testing efforts?4. Use individual resources instead of groups such as Information Systems. It is difficult to manage a group (who is actually working on the project) and may hide overallocation of resources.5. Use Type of Work for personnel resourcesHere is what I need to do for this week:Update the Riordan HR Integration Template based on facilitator feedback and identify the resources and proposed costs needed to complete the project.