Meyer Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per
hour and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in
process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April but not sold. Job C was
started during April but not completed. The job cost sheets revealed the following costs for April:
If no other jobs were started completed or sold determine the balance in each of the following accounts at the end of April:
a. Work in Process____ b. Finished Goods_____ c. COGS_____