Standard
Actual
Material Cost Per Yard
$2.00
$2.10
Standard Yards per Unit
4.5 yards
4.75 yards
Units of Production
9500
5. Calculate the Total Direct Materials cost variance using the above information:
a.
$9262.50 Unfavorable
b.
$9262.50 Favorable
c.
$3780.00 Unfavorable
d.
$3562.50 Favorable
6. Calculate the Direct Materials Price variance using the above information:
a.
$1795.50 Favorable
b.
$378.00 Favorable
c.
$4512.50 Unfavorable
d.
$378.00 Unfavorable
7. Calculate the Direct Materials Quantity variance using the above information:
$4512.50 Unfavorable
b.
$4512.50 Favorable
c.
$4750 Unfavorable
d.
$4750 Favorable