Which of the following statements is CORRECT?
A) For a project with normal cash flows any change in the WACC will change both the NPV and the IRR.
B) To find the MIRR we first compound cash flows at the regular IRR to find the TV and then we discount the TV at the WACC to find the PV.
C)The NPV and IRR methods both assume that cash flows can be reinvested at the WACC. However the MIRR method assumes reinvestment at the MIRR itself.
D)If two projects have the same cost and if their NPV profiles cross in the upper right quadrant then the project with the higher IRR probably has more of
its cash flows coming in the later years.
E) If two projects have the same cost and if their NPV profiles cross in the upper right quadrant then the project with the lower IRR probably has more of
its cash flows coming in the later years.