Question 1
1.
A customer is unhappy with the performance thus far on a project. The customer states that unless scope changes are made at the
contractor%u2019s expense the contractor would be removed from the customer%u2019s preferred bidders list for future contracts. The contractor should.
Answer
Refuse to perform the scope changes.
Perform the scope changes at the contractor%u2019s expense.
Perform the scope changes and then submit an invoice for payment to the customer.
Take no action and hope that the customer will forget about the scope change request.
Question 2
1.
Project sponsors within the contractor%u2019s company have the authority to change the scope of an external customer%u2019s project as they
see fit.
Answer
Have the authority to change the scope of an external customer%u2019s project as they see fit.
Do not have the authority to change the scope of an external customer%u2019s project as they see fit.
Have the authority to change the scope of an external customer%u2019s project only once every six months
Have the authority to change the scope of an external customer%u2019s project as long as the project manager and program
manager are both in accord
Question 3
1.
Generally speaking work packages:
Answer
Are assigned to one functional unit
Are not assigned to one functional unit
Must be assigned to two or more functional units
Must have the approval of the chief executive officer of the company performing the project
Question 4
1.
Consider the WBS shown below:
1.00.00
1.1.0
1.1.1
1.1.2
1.2.0
1.2.1
1.2.2
If the total program costs $100000 and 1.2.1 and 1.2.2 are each $20 K then the cost of 1.1.0 is:
Answer
$20 K
$40 K
$60 K
Cannot be determined
Question 5
1.
A project manager desires a work breakdown structure that goes through 6 levels of detail. Level 3 through level 6 would most likely be
prepared by:
Answer
Project sponsor
Project manager
Subject matter experts
Customer
Question 6
1.
All work packages in a project:
Answer
Do not have to be at the same level of the WBS
Must be at the same level of the WBS
Do not have to be referenced in the Work Breakdown Structure dictionary
Can be changed immediately as long as the project manager and project sponsor agree to do so
Question 7
1.
Which of the following is normally not addressed in a change control board meeting to approve a scope change?
Answer
Cost of the change
Which functional unit will perform the change
Impact on the schedule
Value-added opportunity for the client
Question 8
1.
If the customer%u2019s SOW contains words such as nearly or approximately then:
Answer
The project manager uses his discretion in determining the meaning
The sponsor uses his discretion in determining the meaning
The customer uses his discretion in determining the meaning
Scope creep is unlikely
Question 9
1.
Generally speaking the lowest level in the WBS is referred to as:
Answer
Level 3
Level 4
Level 5
The work package
Question 10
1.
Which of the following would be the first item to be discussed in the initial kickoff meeting for a project?
Answer
Understanding of the requirements
Understanding of the plan
Understanding of the schedule
Understanding of the budget